Project Milestones

Week # Date Event Description
1      
2      
3 1/25 Concept Proposal Determine what language, tools, DB driver, and license we'll use and familiarize ourselves with them.
4      
5 1/8 Initial Client Meeting  
6      
7 2/22 Incremental Release 1 Completed XML Parser for Gimped Data Structures 3.0, basic GUI data population (dynamic filter addition and dynamic filter population), and initial XML-to-Database verification and communication.
8    
9    
10 3/21 Incremental Release 2 Ability to filter/query a single database and basic viewer functionality.
11      
12      
13      
14 4/11 Beta Release GUI-polishing, expanded viewer functionality, and attempt to connect/interact with multiple data sources.
15    
16 5/2 Final Release GIMpeD v2 Released!!